Project Name
North East Link Project - Package 1C
Client
Metro Trains Melbourne
Location
Macleod to Greensborough (Melbourne, Victoria)
Duration
December 2022 to February 2024
Our Services
Principle Contractor
Professional Services
Signalling Construction
Civil & CSR Construction
Testing & Commissioning
Project Description
North East Link Project (NELP) is the overarching project that will connect the M80 Ring Road at Greensborough with the Eastern Freeway at Bulleen. The rail interface component to the project was delivered by Metro Trains Melbourne. Package 1C of the project encompassed Signalling upgrades between Macleod and Greensborough:
Provision of all new main and local CSR assets, including interfacing to existing CSR as required.
Provision of all new signalling assets and modifications to existing signalling assets as required.
Delivery of new signalling power upgrades.
Provision of maintenance access platforms, pathways, driveways, access roads, structures and fencing as required.
Provision and commissioning of new active pedestrian crossing.
T&C all new and/or modified power, signalling, communications, train control systems and associated assets.
Overall delivery and management of the project as Principal Contractor.
Management of all interfacing parties to support the delivery of project scope including obtaining of all necessary permits and approvals.
Decommissioning and disposal of redundant and obsolete signalling, power, track and CSR assets (redundant rail systems).
Our Scope
JBE as the Principle Contractor for delivery of Package 1C scope of works was responsible for delivering the Civil, CSR, Signalling Construction and Testing & Commissioning from start to finish. Our scope of works involved the following.
Principle Contractor requirements for the duration of the project
Site safety management for all subcontractors and third parties
Occupation management
Environmental and sustainability requirements
Construction 4.5km of all new main and local Combined Services Route this included a combination of:
2.5km of trenched and bored CSR
2km of above ground GST cable route
Combination of trenched / bored UTXs
Civil construction to support new signalling assets:
Retaining walls to support Axle Counter GAKs, Signals, Maintenance Access ways
Complete re-build of Wattle Drive Pedestrian crossing
Construction of all new signalling assets between the project boundary, this included:
Installation of 30km of new multicore LV and HV cable to connect new signalling assets
Manufacture, assembly and installation of new Signals
Installation of new Axle Counters and Trainstops
Upgrade of Macleod Relay Room to support installation of new Westrace MKII CBI
Installation of new Axle Counter and Westrace Zone Boxes
Installation of new Xiria switchgear and upgrade of signalling power distribution system from 2.2kv to 3.3kv
Installation of new pedestrian crossing equipment to convert Wattle Drive Pedestrian crossing from passive to active
Decommissioning and removal of redundant infrastructure
Testing and Commissioning delivery including:
Strategy development to minimise risk during major commissioning
Occupation support to provide asset isolations for all construction occupations
Pre-testing of new signalling system prior to commissioning
T&C of new system in major commissioning event
Key Achievements
All scope of works were delivered successfully over 13 occupations. This included two extended major occupations; a 45 day occupation for Civil & CSR works and a 19 day occupation for final commissioning.
Signalling power commissioning 3 months prior to main commissioning event allowing pre-testing to be completed with final power.
90% of construction completed prior to the commissioning event which allowed testing of new Axle counter system in shadow mode for 2 months. This allowed the team to go into the commissioning event with confidence.










