Project Name
Vital Processing Interlocking (VPI)
Upgrade Project
Client
Queensland Rail
Location
Queensland
Our Services
Principle Contractor
Professional Services
Manufacturing
Signalling Construction
Testing & Commissioning
Project Description
11 Interlockings in 11 months!
The vital processing interlocking (VPI) Upgrade project was formed to allow for the renewal of 11 VPI Signalling Interlockings in the Brisbane Suburban Area and upgrade of all signals within the affected stations to LED.
Upgrades Produced the following benefits:
Decreased Faults and Failures
Increased reliability of services
Improved on time running
The refreshing of the VPI interlockings and Signal Equipment rooms included:
Construction, SAT and FAT all Signal equipment rooms
Construction, SAT and FAT all interface Locations cases
Upgrading the line circuit protection
Relay interface including removal of ACO board
Design development of equipment rack and building layouts
Implementation of power supply upgrades
Complete segregation of Internal (clean) and external (dirty) control wiring
Signals upgraded to LED
Stage work all Power distribution
Stage work all signalling interlockings from old to new
Commissioning of Power Equipment Rooms (PERs) Prior to main commissioning to bring the new SER online
Power upgrades to field infrastructure
SIMBID Removal, Dutton Park to Cannon Hill, Interfacing back to Yeerongpilly
Redundant Trackside Equipment Removal
Our Scope:
JBE Signalling fulfilled the role of Principle Contractor for the project and managed the complete requirements for the Workplace Health and Safety, Environment, Test and commissioning with asset handover of the sites, all being achieved on time every time.
Upgrades were delivered over 4 major commissioning’s which required wheel free periods during the signal outages to allow commissioning teams to complete changeover, set to work and commissioning of the signalling system.
Vital to these 4-major commissioning was the implementation of Signalling interlocking and power stage works over consecutive short closures to allow commissioning activities rather than changeover to occur during the main closures.
All Power upgrade works, PER Commissioning’s and the staging of all field equipment was completed outside of the main closure’s. We planned the closures in conjunction with Queensland Rail’s CAU Team with the intention to reduce the length of the main closures with minimal disruption to the rail network. We carefully planned and managed the stage work of signalling upgrades including cables, Power upgrades and PER commissioning’s inside 4 or 6 hour night closures which allowed the JBE team to focus on the Interlocking commissioning’s during the main closure. To make a point of the efficiencies achieved we were able to begin correspondence testing to UTC as soon as the communications bearers and Data at the Control Centre had been changed.
The VPI project was delivered across the following stages:
Service Pack 1 – Beenleigh, Holmview.
2 x 8 meter Signal Equipment Rooms constructed, Tested and Commissioned
Term Loc’s to allow integration to existing network constructed, Tested and Commissioned
Power upgrades to existing Field Locations Modification completed Tested and Commissioned
2 Power Equipment Rooms Integrated, Terminated, Tested and Commissioned
All Signals upgraded to LED
Service Pack 2A – Manly.
1 x 8 meter Signal Equipment Rooms constructed, Tested and Commissioned
Power upgrades to existing Field Locations Modification completed Tested and Commissioned
1 Power Equipment Rooms Integrated, Terminated, Tested and Commissioned
*** Signals upgraded to LED
Service Pack 2B- Lytton Junction, Murrarie, Cannon Hill.
2 x 12 meter and 1 x 8 meter Signal Equipment Rooms constructed, Tested and Commissioned
Term Loc’s to allow integration to existing network constructed, Tested and Commissioned
Power upgrades to existing Field Locations Modification completed Tested and Commissioned
3 Power Equipment Rooms Integrated, Terminated, Tested and Commissioned
All Signals upgraded to LED
Service Pack 3 – Bethania, Kingston.
2 x 8 meter Signal Equipment Rooms constructed, Tested and Commissioned
Term Loc’s to allow integration to existing network constructed, Tested and Commissioned
Power upgrades to existing Field Locations Modification completed Tested and Commissioned
2 Power Equipment Rooms Integrated, Terminated, Tested and Commissioned
All Signals upgraded to LED
Service Pack 4- Fishermans Island SER 1, 2 and 3.
1 x 12 meter 1 x 8meter and 1 x 6 meter Signal Equipment Rooms constructed, Tested and Commissioned
Term Loc’s to allow integration to existing network constructed, Tested and Commissioned
Power upgrades to existing Field Locations Modification completed Tested and Commissioned
2 Power Equipment Rooms Integrated, Terminated, Tested and Commissioned
All Signals upgraded to LED




























